Replacement of an offshore damaged pipeline section of approx 10500m

8 ball pool 8 ball pool 8 ball pool 8 ball pool brawl star hack brawl star hack brawl star hack brawl star hack coin master free spin coin master free spin coin master free spin coin master free spin gardenscapes coins gardenscapes coins gardenscapes coins gardenscapes coins gta 5 money gta 5 money gta 5 money gta 5 money gta 5 money pokemon go pokecoins pokemon go pokecoins pokemon go pokecoins pokemon go pokecoins
gl_heritage

Project Data Sheet

Project : Replacement of an offshore damaged pipeline section of approx 10500 m
Client : TPS
Location : Cercina Rhemoura Pipeline, Offshore Sfax - Kerkenah, Tunisia
Activities : Construction Work / Marine Operations / Diving
Date : 2012

Project performance

Duration :196 Days
Days without LTI :196 Days
Project Start date : 31/10/2011
Project End date : 18/05/2012
Personnel Involved : 75 Prs (39 Onshore / 36 Offshore)
Project Manhours : 80422 Manhours

gl_heritage

The Project comprise the following phases :

  • Pipe Transfer from Rehmoura storage premises to the site in Kerkennah
  • Channel excavation for a total length of 800 m as pipe launch area
  • Pipe laying operation
  • Pipe welding and non destructive testing inspection o Pipe Coating, flushing and gauging prior launching.
  • Pipe towing to the offshore Installation pontoon
  • Offshore replacement of the damaged pipeline section
  • Gauging of the whole pipeline
  • Hydraulic Test of the pipeline
  • Trenching in the vicinity of 10.5km zone of the old pipeline connection area.
  • Backfilling of the channel and burial of the new pipeline section

Tasks :

  • Pipeline Welding, Test and Inspection Onshore Offshore
  • Trenching
  • Pipeline Burial
  • Marine operations